November 20, 2012 - 1:50am | by seana and marissaIt's getting cold in Tomales!
Which means it's almost Winter, which means it's almost January 31st, which means it's almost time to build the creamery if we want to stay on track!
Amazingly, Seana and Dave finished composing all the drafts for the Building Dept. to review before being officially submitted. To me, this feels like a huge step forward. Also, the cheese vat is due to arrive soon! It feels like waiting for a baby to be born...is it here yet?? Have we reached the due date?? I'm sure it's even more exciting for Seana and Dave, since it's really their vat and their creamery being developed. But ultimately I, too, will use the space (hopefully sooner rather than later), so I feel pretty elated at the progress. It doesn't actually feel real yet, as most dreams-come-true probably don't at first. But I bet once the jackhammer hits the concrete, reality will hit me, too.
All is not well...not without permits
November 1, 2012 - 6:52pm | by seana and marissa
It's November. My goal is that the creamery will be ready to rock on January 15th. We have yet to obtain ANY permits. Needless to say, I’m feeling anxious and frustrated with the slow pace at which things seem to be moving. On Monday I had a massive migraine for the first time in many months, hmm… I wonder what could be the cause.
Making Progress and Cheese
October 22, 2012 - 7:33pm | by seana and marissaLots needs to be done to get the creamery project moving, but daily life seems to be getting in my way. Fortunately Seana and Dave are dedicating a lot of their time, and are making most of our progress!
We’re currently trying to obtain permits for plumbing, electrical, and water use. I actually thought this part of the process would go much quicker than it has, since the structure is sound and not too much needs to be done, relatively speaking. But permits take a lot of planning and negotiating. And you have to be willing to revise your plan and negotiate more. So while it’s a full-time job to get these things figured out and crossed off the to-do list, we go to our real jobs during the day, and work on permits in the hours between.
100 days and $100,000 to turn this building into a creamery?
October 8, 2012 - 9:24pm | by seana and marissaThis blog will chronicle the planning, permitting, financing (including exact dollar amounts) and building of a micro creamery on a ranch in Tomales, California. It will feature alternating posts from 2 different people, Seana Doughty and Marissa Thornton, who have joined forces to help each other achieve their cheesemaking dreams and goals. Allow us to introduce ourselves.....